The Hatch Report   Hatch

Arctic conditions a challenge for Meadowbank mine

Meadowbank gold project

The process design for the greenfield Meadowbank gold mine in Nunavut, a Canadian territory, is based on a conventional gold plant flow sheet. The mill is designed to operate with a throughput capacity of 8,500 tonnes per day.

The project is a logistical challenge because site access is limited to the short Arctic summer. More than 50,000 tonnes of materials and equipment had to be shipped by barge over three 10-week summers between August and October.

Once in operation, Meadowbank ore will be accessed using drilling and blasting with truck haulage to a primary crusher adjacent to the mill. Waste material from the pre-stripping will be used as bulk construction materials for dikes, and fill material around the site.

The Meadowbank project is located near the western shore of Hudson Bay, and has expected gold reserves of 3.6 million ounces (32.8 million tonnes at 3.45 g/t). Startup is expected in the first quarter of 2010.

Four major buildings including the process plant, truck shop and power plant were erected during the summer of 2008. This allowed the concrete and equipment construction to continue indoors during the minus 50°C Arctic winter.

To ensure that the local population had a role in the development of the mine, there was close collaboration between the owner and Inuit stakeholders, as set out in the Inuit Impact and Benefits Agreement (IIBA).

Hatch is providing detailed engineering, procurement and construction management support for the 8,500-t/d gold processing facility, which includes

  • Primary crushing and conveying
  • Covered ore storage stockpile
  • Concentrator
    • SAG/ball milling
    • Leaching
    • Refining
    • Detoxification treatment including SO2 generation
    • Tailings disposal
  • Infrastructure
    • 28-MW diesel-power generating plant
    • 10-bay truck shop and office complex
    • Site satellite communications
    • Incinerator building
    • Sewage treatment facility
    • Freshwater supply
    • Reclaim water supply
    • Overland piping
    • 40 million-litre diesel storage and dispensing facility at
      the town of Baker Lake and a 5.6 million-litre diesel storage
      and dispensing facility at the mine site

Hatch also provided construction and logistics support for the project.

For further information, please contact Bruce Rustad: BRustad@hatch.ca

 

Hatch Corporate Office
Sheridan Science & Technology Park
2800 Speakman Drive
Mississauga, ON, Canada
L5K 2R7

Tel:
Fax:

+1 905 855 7600
+1 905 855 8270

 
www.hatch.ca